Use this page for a single rectangular slab of uniform thickness: a shed base, a patio, a path slab, or a garage floor panel that is the same thickness all the way through. Measure to the inside of the formwork. Enter length, width, and thickness separately. If the slab has thickened edges, beams, or a pit, calculate those extra prisms on the Concrete Calculator (or as a second slab volume) and add them to this result.
Formula
Volume = length × width × thickness × (1 + waste ÷ 100)
Bags = round up (volume ÷ yield per bag). Use the same volume units.
The conversion that most often goes wrong is thickness. A 4 inch slab is 4 ÷ 12 ft thick (about 0.333 ft), not 4 ft. The unit lists do that conversion when you set them correctly. After you have a volume, cubic yards = cubic feet ÷ 27.
Waste stays at 0% until you enter a figure. Uneven subgrade and over-excavation are common reasons to allow a margin on a slab on grade. Use a figure you are willing to stand behind for your site, then round the order the way your plant requires.
Worked example 1 — 12 ft × 10 ft patio, 4 in thick
Inputs
- Length: 12 ft
- Width: 10 ft
- Slab thickness: 4 in
- Waste allowance: 10%
- Bag yield for the bag comparison: 0.60 ft³ per 80 lb bag
Working
- Thickness in feet = 4 ÷ 12 ≈ 0.333 ft
- Neat volume = 12 × 10 × (4 ÷ 12) = 40 ft³
- After 10% waste = 44 ft³
- Cubic yards = 44 ÷ 27 = 1.63 yd³ (about 1.25 m³)
- 80 lb bags = 44 ÷ 0.60 = 73.33 → 74 bags
That is a large number of bags to mix before the first batch starts to stiffen. Use the yardage to talk to a ready-mix supplier, and use the bag count only if you deliberately plan a bagged pour.
Worked example 2 — 4.0 m × 3.0 m slab, 100 mm thick
Inputs
- Length: 4.0 m
- Width: 3.0 m
- Slab thickness: 100 mm
- Waste allowance: 8%
- Bag yield: 0.0117 m³ per 25 kg bag (replace with the label)
Working
- Thickness = 0.10 m
- Neat volume = 4.0 × 3.0 × 0.10 = 1.20 m³
- After 8% waste = 1.296 m³ (about 1.70 yd³)
- 1.296 ÷ 0.0117 ≈ 110.7 → 111 bags of 25 kg, if that is the labelled yield
Buying guidance
- Confirm how the plant wants the ticket written (cubic yards or cubic metres) and whether they charge a short-load fee below a minimum volume. This page does not quote those fees.
- If you are using bags, stage only as much water and mix as you can place in one working window.
- A slab usually sits on a compacted base. Estimate that stone separately with the Gravel Calculator; do not assume the concrete volume includes the base.
- Thickened edges are easy to miss. Measure them and add the extra volume so the truck is not short at the perimeter.
Frequently asked questions
What thickness should I use? The calculator will not choose a thickness for you. Use the thickness on your drawing, permit, or the advice of a qualified professional. Typical patio and shed figures you see in public guides are starting points, not a design for every soil condition.
How do I add a thickened edge? Calculate the uniform slab first. Then calculate the extra width and depth of the edge as one or more additional rectangular volumes and add them.
Why is my result twelve times too large? The thickness unit is probably still in feet while you typed an inch figure, or the other way around. Check the unit lists before you order.
Can I enter square footage instead of length and width? Not on this form. If you already know the area, you can still use length and width that multiply to that area, or measure the rectangle on the Square Footage Calculator first.
Do I need a waste allowance on a perfectly level, well-formed slab? Maybe a smaller one. The box is yours to set. A neat theoretical volume rarely matches the hole in the ground exactly.
Does this include wire mesh, vapour barrier, or isolation joint material? No. Those are separate take-offs.
Related calculators
Results are planning estimates. Recheck measurements and product labels before ordering. See our Disclaimer.