How the concrete calculator works
Use this calculator when you have one rectangular form, and you will pour that same size more than once — for example, identical pad footings, pier blocks, or repeated fence-post footings. Measure the inside of one form: length, width, and pour depth. Enter how many forms share those dimensions. If some footings are a different size, run the calculator again for that group and add the two volumes before you order.
The result is a planning volume in cubic metres, cubic feet, and cubic yards, plus a bag count if you enter a bag yield. The tool does not size reinforcement, mix strength, or frost depth, and it does not replace a structural drawing.
Formula
Volume = length × width × depth × number of identical pours × (1 + waste ÷ 100)
Bags = round up (volume ÷ yield per bag). Use the same volume units.
Convert every dimension into the same unit before you multiply. A depth entered in inches must be treated as inches, not as feet; the calculator converts units for you when you pick them from the lists. Cubic yards = cubic feet ÷ 27. Ready-mix plants commonly sell concrete by the cubic yard in the United States and by the cubic metre in the United Kingdom, Canada (often either), and Australia.
The waste box starts at 0%. Add an allowance if you expect uneven ground, form movement, or spillage. Many planning discussions use something in the region of 5–10% for formed work, but the right figure depends on the site. Ask the supplier or contractor what they would allow for your pour.
Worked example 1 — eight 2 ft pads (US customary)
Inputs
- Length: 2 ft
- Width: 2 ft
- Pour depth: 12 in (1 ft)
- Number of identical pours: 8
- Waste allowance: 10%
- Bag yield used for the bag count: 0.60 ft³ per 80 lb bag, 0.45 ft³ per 60 lb bag, or 0.30 ft³ per 40 lb bag (typical planning yields; use the label)
Working
- Volume of one pad = 2 × 2 × 1 = 4 ft³
- Eight pads = 32 ft³
- After 10% waste = 32 × 1.10 = 35.2 ft³
- Cubic yards = 35.2 ÷ 27 = 1.30 yd³ (about 0.997 m³)
Bags, rounded up
- 80 lb bags at 0.60 ft³: 35.2 ÷ 0.60 = 58.67 → 59 bags
- 60 lb bags at 0.45 ft³: 35.2 ÷ 0.45 = 78.22 → 79 bags
- 40 lb bags at 0.30 ft³: 35.2 ÷ 0.30 = 117.33 → 118 bags
At this volume, compare bag mixing time with a short load of ready-mix. The calculator will still report both yards and bags so you can choose.
Worked example 2 — six 600 mm pads (metric)
Inputs
- Length: 600 mm
- Width: 600 mm
- Pour depth: 400 mm
- Number of identical pours: 6
- Waste allowance: 10%
- Bag yield used for the bag count: 0.0117 m³ per 25 kg bag (the staging default, which scales the common 80 lb yield; replace it with the yield on your 25 kg bag)
Working
- One pad = 0.60 × 0.60 × 0.40 = 0.144 m³
- Six pads = 0.864 m³
- After 10% waste = 0.9504 m³
- About 33.56 ft³, or 1.24 yd³
- 0.9504 ÷ 0.0117 ≈ 81.2 → 82 bags of 25 kg, if that yield is what the bag states
Buying guidance
- Read the yield, not only the bag weight. Two 25 kg bags from different plants can place different volumes.
- Common bagged sizes you will see in these markets include 40, 60, and 80 lb sacks, and 20 or 25 kg sacks. Enter the size you will actually carry and mix.
- For several cubic yards or more, ready-mix is usually the practical route. Ask the plant about their minimum load and how they want the order rounded (often to the next 0.1 or 0.5 cubic yard, or to a fraction of a cubic metre).
- Do not treat leftover concrete as a reason to under-order. Running short mid-pour is harder to fix than having a small surplus.
- Place different sizes as separate calculations, then add the volumes, rather than averaging the dimensions.
Frequently asked questions
Does this calculator work for a single patio slab? It will return a volume if you set the number of pours to 1, but the Concrete Slab Calculator is the clearer tool for one flat slab of uniform thickness.
How do I handle a depth given in inches? Choose inches in the depth list and enter 4, 5, or 6 as printed on the drawing. Do not enter 4 if the unit is still set to feet.
Are the default bag yields official? No. They are editable planning defaults. The page already warns you to enter the values printed on the product label.
Should I add waste to bagged and ready-mix jobs? Add waste when the forms, subgrade, or placement method could use more concrete than the neat volume. Enter 0% only if you have already included that margin somewhere else.
Can I pour footings and a slab as one input? Only if every piece is the same rectangle. A slab plus a narrower footing should be calculated as two volumes and then added.
Does the result include rebar, mesh, or formwork? No. It is a concrete volume estimate only.
Why do I see cubic metres, cubic feet, and cubic yards together? So you can talk to a supplier in any of the four target markets without a separate conversion step.